ARC HeRO Project
As a large civic facility with year-round operations of a pool and community centre and a seasonal arena, the Abbotsford Recreation Centre (ARC) is a significant source of carbon pollution for the City of Abbotsford. To support the City’s climate action goals in the Official Community Plan, the ARC Heat Recovery and Optimization (HeRO) Project was identified and aims to reduce energy use and carbon pollution while not only improving and extending the life of the City’s recreation assets, but also increasing patron comfort throughout the facility. Project elements include retrofitting the rec centre’s Heating Ventilation and Air Conditioning (HVAC) system, enhancing wheelchair pool lifts, and interconnection of all mechanical systems to save energy and efficiently share thermal (or heat) energy throughout the facility. These improvements are expected to reduce the facility’s energy consumption by an estimated 41.37% and greenhouse gas emissions by 455 tonnes annually.
Construction Details:
Throughout the construction period, City contractors will be installing piping throughout the facility to connect the aquatic centre with the arena and the community centre. This piping will carry water that is heated by waste heat captured from the aquatic centre and arena to other areas of the building where heat is needed. This waste heat would typically be released into the surrounding air outside. Once the heat is transferred, the cool water will be returned and re-heated, completing the heat recovery loop.
New digital controls will also be installed to ensure that building operators are able to adjust and monitor all aspects of the new system to provide consistent and comfortable temperature conditions throughout ARC.
Project Benefits
ARC is made up of three major recreation areas: the aquatic centre, the arena and the community centre. These were constructed in 3 separate phases in 1972, 1995 and 2008. As a result, various systems throughout the facility, like heating and cooling, are not integrated and most need updating or replacement. This project provides an opportunity to integrate the three systems and improve system efficiency through new technology that will allow the facility to capture waste heat for use in other areas of the facility, thereby decreasing energy use and reducing carbon pollution.
The City is doing the ARC HeRO project to not only improve the recreation experience for patrons by upgrading heating and cooling systems to make the facility more comfortable, but also demonstrating our ongoing commitment to environmental sustainability by decreasing our energy use and reducing our carbon pollution. The HeRO project will reduce natural gas consumption, improve energy efficiency, make use of waste heat onsite while also improving the temperature and overall comfort of spaces throughout the ARC facility.
System commissioning, testing, and optimization are continuing behind the scenes at ARC. Testing has determined some additional modifications are required within the arena’s ice plant to achieve target performance. As a result, some minor additional construction work will be completed on the east side of the building in the coming weeks. Public impacts from construction will remain minimal for the remainder of the project. Most contractor trailers have been removed from site, restoring parking along the west side of ARC.
Mechanical and electrical construction has been successfully completed, and system commissioning with functional testing is now in progress. During this phase, heat recovery chillers will be brought online and gradually ramped up, delivering base-load heating to pools and domestic hot water by capturing and reusing energy that would otherwise be wasted. Finishing work in the new mechanical room is also advancing and is scheduled for completion by year’s end. Public impacts from construction remain minimal, and contractor trailers located along the west side of ARC are planned for demobilization in January 2026.
Installation of interfacility piping at ARC is nearing completion. Commissioning of the new mechanical systems is underway. The new high-efficiency boilers are now fully operational, providing base load heating to both the aquatic centre and the arena. In the coming weeks, heat recovery units will be commissioned. Construction impacts to the public remain minimal, with most remaining work confined to non-public areas. Commissioning and optimization efforts will continue throughout the fall, with substantial completion anticipated in December 2025.
Piping interconnections throughout the facility have been completed. Installation of new mechanical equipment is continuing throughout the summer. New mechanical room construction and outfitting will be complete in September. Upstairs mezzanine room will remain at reduced capacity until early September when work in upper fan room is complete.
Construction activities at ARC have progressed, with new piping installations throughout the facility to integrate the various heating systems of the building. The majority of construction remains confined to mechanical spaces. Work in public areas has been scheduled to occur outside of operational hours, thereby minimizing disruptions to patrons. The attached images illustrate the scope of current construction efforts in public areas.
The contractor has setup the site trailers and laydown areas along the west side of the building. Construction fencing is also being installed around the arena mechanical equipment in preparation for site works to accommodate new mechanical equipment. Within the building, work is currently limited to mechanical spaces and should cause minimal impacts to patrons.
Starting near the end of January until the end of 2025, there will be intermittent construction work, resulting in possible noise impacts and interruptions to space use or programming in various areas throughout the arena, aquatic centre and community centre as well as the café and washrooms. At times, the parking lot and facility access may also be affected. These impacts may last for a few days or up to a few weeks at a time.
The construction schedule has prioritized work time during when ARC is closed to the public including overnight to minimize the disruption to patrons whenever possible. More detailed information on the extent of these disruptions will be shared as timelines are finalized leading up to the work.
Patrons will be notified of construction impacts through signage will be posted in the facility, and notices on City social media for any program or space disruptions as early as possible, once specific construction and impact timelines are confirmed. Advance notice of program or space disruptions will also be provided to patrons through the online Direct2Rec system when possible.
This project is funded in part by the Government of Canada through the Green and Inclusive Community Buildings Program and by the BC Provincial Government through the Growing Communities Fund.

Thermal Storage Tank
December 2025

Exterior Piping Runs at ARC
December 2025

October 2025
Aquatic Mechanical Room Equipment

October 2025
Ice Plant Heat Recovery Piping

October 2025
Arena Mechanical Room Equipment

Thermal Storage Tank Enclosure

New Boiler Installation

Abbotsford Recreation Centre
Temporary pool heating boilers while new boiler system is installed

Abbotsford Recreation Centre
Thermal storage tank and piping connections

Abbotsford Recreation Centre
New interconnecting pipeworks

Abbotsford Recreation Centre
New interconnecting pipeworks and arena heat recovery heat exchanger

ARC Arena
New interconnecting pipeworks within arena

ARC Arena
New interconnecting pipeworks within arena

Contractor Office Location
February 2025

Abbotsford Recreation Centre
Piping inside Abbotsford Recreation Centre

2499 McMillan Road

